Installation 5-5
SG4000 Installation and Operation Manual
Figure 5-5 illustrates a front and side view of the strand mounting clamps.
Figure 5-5
Strand mounting clamps – front and side view
456
Clamps Clamp
To mount the SG4000 to the strand wire:
1 Loosen the 5/16 × 18 strand clamp bolt located on each mounting bracket.
2 Lift the node such that the clamps are level with the strand and slide the node back until
the strand engages the strand clamps.
Do not tighten the hex-head bolts at this time. This enables the clamps to slide along the
strand wire until the housing is finally positioned with respect to the cables.
3 Verify that the node is within 5 degrees of hanging straight up and down.
3 When the housing is in the required position, torque the two strand clamp bolts to
10 to 12 ft-lbs.
4 Re-install any modules and electronic components that were removed before the housing
was installed.
Optional Strand Bracket Mounting
In applications where a vertical approach to mounting the node is preferred, you can use the
SG2-style strand bracket assembly. This optional kit contains one mounting bracket, two spacer
blocks, and two 5/16 × 18 bolts. You can order this bracket kit through your local Motorola sales
representative.
To install the optional strand bracket and mount the SG4000:
1 Remove the factory-installed strand clamps.
2 Remove the components from the kit and position them as illustrated in Figure 5-6.